By Lisa Yang 
            
              
                  
                    Accessibility  improvements were made in several areas as part of the Hwy 169/Pokegama Avenue  project in Grand Rapids. Crosswalk markings will be put in next year and the  project will be complete in June 2013. Photo by Dana Marrier  | 
               
             
            Construction is wrapping up for this year on Hwy  169/Pokegama Avenue in Grand Rapids, a project that features several accessibility  improvements for pedestrians, including: 
            
              - Curb ramps with detectable warnings
 
              - New sidewalks with accessible driveway crossings
 
              - Accessible pedestrian signal upgrades at four  intersections
 
             
            “We recognized this project as an opportunity to provide a  long-term fix for all users,” said Krysten Saatela, project development  engineer. “Along with replacing underground utilities and improving pavement  smoothness for drivers, MnDOT staff also applied careful engineering along the  sidewalks to ease pedestrian travel between nearby residences and businesses.” 
            Shortly after construction was completed on the first stage  of the project along the west side of Hwy 169, MnDOT staff noticed an increase  in the use of the new sidewalks, curb ramps and accessible, signalized  crossings. 
            “These accessibility improvements help change peoples’  ability to get around,” said Dana Marrier, District 1 chief inspector.  
            A resident who is a double-amputee wheelchair user commented  that before the improvements were made, it was challenging for him to navigate  the sidewalk, according to Marrier. That resident is now able to wheel up and  down the area every day. 
            “It greatly improves the quality of life for individuals  with and without disabilities,” Marrier said. 
            Several other employees were involved in planning and  implementing the accessibility improvements, including Kevin Rohling, project  engineer; and Todd Grugel, Americans with Disabilities Act program engineer. 
            During construction, Grugel and his team visited the project  with Rohling and discussed widening the sidewalks in areas where there was  sufficient right of way in order to make it more user-friendly, which allowed  for better driveway and curb ramp construction. 
            “Kevin listened to the ideas, negotiated a work order with  the contractor and ran with them,” Grugel said. “It was by far the best money  we could have spent from an ADA perspective.” 
            Rohling said the department is better able to meet ADA  compliance guidelines in a reconstruction situation because “we are working with  more pieces of the puzzle.” 
            “An example of this would be, we can position such things as  a drainage structure so it is not too close to a ramp and affecting  slopes.” 
            Before the final plan was to be turned in, Grugel and his  staff worked with District 1’s Design Office and made some modifications to the  plan. They also piloted an enhanced, special provision called ‘1803 Prosecution  of Work’ for special project ADA requirements. These requirements put more  responsibility on the contractor to coordinate the ADA work, as well as  complete and submit the ADA compliance check lists for payment. 
            Overall, the project has been well received by the public,  according to Rohling and Grugel. The work this year, completed ahead of  schedule, provides a new continuous center left turn lane from one end to the  other and a continuous right turn lane for three blocks of the reconstruction  section. This allows for more efficient and safer travel through a busy corridor  where many fast food restaurants are located. 
            “From an ADA standpoint, this is the best overall project  I’ve seen in my two and a half years of monitoring ADA projects on a statewide  basis,” Grugel said. “Not only was the project completely compliant, but it was  easy to notice the attention to detail put in by both the contractor and MnDOT  field staff that made the new curb ramps, sidewalks, driveways and crosswalks truly  user-friendly. 
            It certainly goes to show that a project can fail or succeed  on many levels or stages, but a dedicated and conscientious project team can  make all the difference.”  |