  
                 The Hwy 52 Lafayette  Bridge over the Mississippi River in St. Paul is one of the 172 bridges identified in MnDOT’s Trunk  Highway Bridge Improvement Program, which is intended to accelerate the repair  or replacement of the state’s fracture critical or structurally deficient  bridges over 10 years. To date, 65 of those bridges are substantially complete,  with another 12 bridges expected to be complete by the end of the 2012  construction season. Photo by Nick Carpenter  | 
               
           
            Five years after the Interstate 35W  bridge in Minneapolis collapsed into the Mississippi River, a number of changes  to bridge management programs here in Minnesota and nationally have been  adopted to ensure the overall safety of the nation’s bridges.   
            “Many lives were changed on Aug. 1,  2007,” said Nancy Daubenberger, state bridge engineer. “We have worked very  hard to make sure that this tragedy has resulted in positive bridge safety improvements,  both in Minnesota and nationally.” 
            After  months of investigation during 2007 and 2008, the National Transportation Safety Board determined that the probable cause of the collapse,  which killed 13 people and injured 145 others, was inadequate load capacity due  to a design error of some of the bridge’s gusset plates. According to the report, the  failure occurred under a combination of factors—substantial increases in the   weight of the bridge from previous modifications and the concentrated  traffic and construction loads on the day of the collapse. 
            “If  the bridge had been properly designed, these additional loads would have been  within the appropriate safety factors,” Daubenberger said. “The 35W bridge  collapse highlighted the need for increased national attention to bridge  safety, and drove several improvements in state transportation department  bridge programs, including MnDOT’s.” 
            Notable  changes in MnDOT’s bridge program since 2007 include: 
            
              - Major bridges now  require a formal independent peer review during design to minimize the risk of  a critical design error. MnDOT hires separate engineering firms to  conduct the reviews. 
 
              - Statewide  staffing to perform bridge maintenance has increased by about 50 percent, or 55  positions.
 
              - MnDOT has conducted research into advanced bridge monitoring techniques, such as acoustic  emissions monitoring and infrared thermography. The department uses these techniques  where appropriate, but still considers traditional visual and physical  inspection as the foundation of condition assessment, according to Tom  Styrbicki, bridge construction and maintenance engineer.
 
              - MnDOT has changed  its bridge construction specifications to place limits on equipment and material stockpiles  on bridges.   
 
              - Specific  performance measures have been instituted for bridge inspection and  maintenance. These measures place performance targets on timeliness of  inspections and maintenance accomplishments.
 
              - MnDOT has  developed a customized, state-of-the-art Structure Information Management System. Within the system, bridge inspection and maintenance  actions are integrated to identify condition, plan and prioritize maintenance  need, document and report on accomplishments, and assess benefit of maintenance  activities.
 
             
            In addition, the 2008 Legislature  provided $2.5 billion over 10 years to replace or repair the state’s fracture  critical and structurally deficient bridges, such as the Hwy 52 Lafayette  Bridge in St. Paul, currently under construction, and the Hwy 23 DeSoto Bridge  in St. Cloud, which already has been replaced. Of the 172 bridges identified  and funded by the Chapter 152 program, an estimated 120 bridges will be under  contract to be replaced or rehabilitated by June 30, 2018. The remaining bridges were either: 
            
              - Under  construction at the time the program was established 
 
              - Classified as  lower priority and not required to be funded as part of the program 
 
              - Privately owned  or needing no work other than routine maintenance until after 2018  
 
             
            The status of the 172 bridges is as follows: 
            
              - 65 bridges  substantially complete
 
              - 12 other bridges  to be complete by the end of the 2012 construction season
 
              - 65 bridges  scheduled to be under contract for repair or replace in 2013-2018
 
              - 27 bridges judged  to need only routine maintenance until beyond 2018
 
              - 3 bridges are  either privately owned or do not carry state trunk highway traffic
 
             
            The most recent Chapter 152 update report can be found at www.dot.state.mn.us/planning/program/pdf/CH152AnnualInventoryReport2012.pdf.  
The  NTSB also recommended to the Federal Highway Administration and the American  Association of State Highway and Transportation Officials  changes in  bridge management on a national level, including developing and implementing a  bridge design quality assurance/quality control program for bridge owners; developing  specifications and guidelines for bridge owners to ensure that construction  loads and material stockpiles do not overload structural members or connections;  and modifying and updating manuals and training, especially with regard to  inspecting and responding to gusset plate issues. |